Success Stories
Novant Health: NFPA 110 Audible Alarming Part 2
Novant Health and Carolina CAT seek help in an emergency generator audible alarming compliance situation. (Read part 1)

Novant Health
Novant Health Presbyterian Medical Center is a nonprofit 622-bed tertiary medical center in Charlotte, NC. As a Level 1 facility, their generators are required to comply with National Fire Protection Association (NFPA) 110 standards.
According to NFPA 110, a standard for inspecting and testing emergency generators, all Level 1 generators (generators that could result in the loss of life or serious injury, should they fail) must have remote visual and audible alarming to alert personnel to the presence of generator safety and shutdown indications.
The standard states: “The minimum remote alarm annunciation is to alert personnel at a constantly attended station somewhere on the site when the facility is in use as a Level 1 system. If the site is not continuously occupied, ‘network remote’ should allow people at another site to know the operating status of the equipment.”
There aren’t too many companies who would have been able to answer our SOS at the drop of a hat, especially without much previous experience with Deep Sea and Baseler generator control panels. But Affinity Energy is one of them.
–Jerry Beavers, Carolina CAT
Challenge:
On a Wednesday afternoon in March 2018, Novant Health was cited in a DHSR (Division of Health Service Regulation) audit because the remote annunciator for the D-wing generator failed to produce an audible alert when tested. If not fixed in 48 hours, they faced a $25,000 per day fine.
Novant Health and their generator partner, Carolina CAT, called Affinity Energy that same evening to ask for assistance and expedite a proposed project to upgrade the existing NFPA remote annunciators. Affinity Energy engineers visited Novant that evening to verify communications to the existing Deep Sea DSE 8710 generator control panels using Modbus TCP on the hospital network. Since all the generators had this control panel and were already on the network, the path was cleared for integrating existing generators.
Solution:
Over the next two days, and with Carolina CAT’s help, Affinity Energy engineers built and tested Deep Sea DSE 8710 integration with the NFPA touchscreen annunciator panel originally created by Affinity Energy in a previous project for Novant, and integrated the remaining 14 of Novant Health’s generators.
Originally, Affinity Energy integrated two Caterpillar EMCP 4.2 generators into the NFPA annunciator panel, but because the remaining 14 generators used Deep Sea DSE 8710 control panels, Affinity Energy had to build an entirely new template for the annunciator panel.
By the end of the 48-hour grace period, Affinity Energy’s touchscreen annunciator panel solution displayed all Novant generators, and Carolina CAT technicians had fully tested the failed D-wing generator annunciation for DHSR approval.
Results:
After demonstrating the D-wing annunciator solution, Novant Health asked the DHSR for a 30-day extension to make additional control upgrades.
While integrating Deep Sea DSE 8710 control panels into the remote annunciator panel, Carolina CAT and Affinity Energy determined some of the alarms required by NFPA 110 Level 1 were not integrated into the Deep Sea control panels. Providing the missing alarms would require re-programming of the DSE 8710 control panels.
However, due to the customer’s negative history with the failed Deep Sea annunciator product and lack of timely customer support, they sought to upgrade and retrofit the existing generator control panels, as well as incorporate the following features into the Affinity Energy remote annunciator panels:
- Alarm rearming after user acknowledgement to reengage the siren and require operator intervention.
- Alarm emails that not only allow alarm viewing at the panel, but the ability to email alarm details to on-call personnel and management.
- A second, independent control panel installed in a different building.
The proposed solution would involve Carolina CAT replacing all Deep Sea 8710 control panels with either Basler DGC-2020 Digital Genset Controllers or Caterpillar EMCP 4.2 Generator Set Controllers and Affinity Energy upgrading the capabilities of the existing remote annunciator panel, developing a Basler DGC-2020 template, and installing a second independent panel in plant engineering.
After Novant Health agreed, Carolina CAT and Affinity Energy mapped out a plan to upgrade the control panels and test the remote annunciator for 13 of the 14 generators. (One of the 14 generators was a temporary generator and scheduled to be removed within several weeks.) In the end, Carolina CAT staffed the project and worked some incredible hours to meet the 30-day deadline, which involved not only installing new panels, but testing alarms at the remote annunciator panel at switchboard operations and plant engineering.
Now that Novant Health has a direct interface to each generator’s control panel through smart communications, the next step is to demonstrate automated Joint Commission reporting using real-time status and generator readings from the generator control panels.
Success Stories
Charlotte Pipe & Foundry
Managing energy costs for large industrial facilities can be challenging. Like many manufacturers, Charlotte Pipe and Foundry (CPF) viewed high energy costs as a necessary…
QTS Data Centers
Data centers and cloud storage are integral components of the digital age. Customers of data centers, both businesses and individuals, demand uninterrupted access…
Concord Energy
Municipalities looking for a renewable energy source can simply look to their local landfill. First, we won’t be running out of trash anytime soon. Second, the organic waste in landfills…
UVA Medical Center - Logs & Alerts
Because of the University of Virginia Medical Center's rapid growth, it was difficult to keep track of and access event details in their central energy plant. When generators tripped...
UVA Medical Center - ATS SUBMETERING
UVA Medical Center has dozens of ATSs distributed throughout campus, but no way of determining if loads were growing over original infrastructure load specifications...
UNC Chapel Hill - Temperature Control
UNC Chapel Hill needed a solution to regulate temperature in a thousand research rooms...without being held hostage to proprietary programming technology...
Solar SCADA & Field Controls
A large solar developer with concurrent solar projects needed to finalize SCADA at eight sites before the end of 2017 in order to meet tax equity implications...
Steel Mill - Active Power Management
Affinity Energy helps a high-power steel mill in the southeast maximize output, upgrade their EPMS software, troubleshoot meters, and maintain visibility to voltage disturbances.
Novant Health - Alarm Annunciator
Novant Health and Carolina CAT seek assistance from Affinity Energy in an emergency generator audible alarming compliance situation.
NextEra - SCADA & Field Controls
Two 80-MW sites required significant changes to the PLC code and SCADA HMI due to the incorporation of a new OEM's inverters.
Chesapeake Bay Bridge Tunnel
The Chesapeake Bay Bridge-Tunnel Commission chose Affinity Energy to upgrade their power monitoring SCADA system. The completed system...
Southeast Hospital System Alarming
A large hospital system in the Southeast with multiple Central Energy Plants needed a way to keep an eye on SCADA and critical alarms at three plants...with just one operator.
Woman's Hospital - GE Integration
Affinity Energy was chosen by GE for a simple SCADA integration, but ended up also solving several frustrating power monitoring issues for end-user Woman’s Hospital.
Novant Health - Generator Alarming
Novant Health and Carolina CAT seek a new generator audible alarming solution to simplify NFPA compliance for the addition of new engine-generators.
UVA - PME SCADA Migration
A large university transitions automation systems to a single power management system, and encounters challenges in user interface design and navigation along the way.
DC Blox - Customized SCADA
Affinity Energy architects a high availability, scalable EPMS and SCADA solution that manages critical equipment & reports customer power usage.
Conetoe Solar Farm
In 2015/2016, Duke Energy Renewables wanted to outfit their new 80MW solar farm in Conetoe, North Carolina with controls and insight into each critical operational piece of equipment...
Duke Energy Solar Site Monitoring
Duke Energy wished to integrate solar data from North Carolina sites acquired from other solar installers into their overarching SCADA system of renewable resources...
JLL/Bank of America - CFMS Failure
When the CFMS unexpectedly failed for Bank of America, JLL turned to Affinity Energy for a quick turnaround to get the system back online.
Noncompliant Ramp Rate Response
A 20MW site in violation of their interconnection agreement looked to Affinity Energy to correct ramping behavior and remove oscillation in curtailed output.
Situational Awareness HMI
A landfill gas to pipeline project looked to Affinity Energy to deploy a highly sophisticated controls and monitoring solution with situational awareness design and ISA-101...
Mercedes-Benz Stadium - EPMS
Mercedes-Benz Stadium needed an electrical power management system (EPMS) to ensure computing continuity to control stadium lights and broadcasts...